ENVIRONMENT
Physical survey and environmental and social impact assessment study of the construction of the 63-kV Segou – Markala – Niono (105 Km) power line
Client:
|
EDM SA |
| Date: |
2007 |
| Partner: |
NONE |
| Cost of services: |
62 million FCFA (102 000 €) |
| Description : |
The project consisted in the definition of a legal and institutional framework, the determination of an environmental baseline, the development of a social and environmental impact assessment, the identification of potential mitigation of said impacts, the development of a Social and Environmental Management Plan, public information and consultations, determination of appropriate compensation for right-of-way expropriations, the preparation of a relocation plan, and, finally, submission of recommendations regarding training for the staff of government departments/agencies responsible for the environment.
|
Environmental and social impact survey (Malian territory) of the Ghana – Burkina – Mali 225-kV (405 km) power interconnection
Client:
|
KEPCO (Korea) |
Date: |
2007-08 |
Partenr: |
NONE |
Cost of services: |
45 million FCFA (69 000 €) |
Description : |
The project consisted in the definition of a legal and institutional framework, the determination of an environmental baseline, the development of a social and environmental impact assessment, the identification of potential mitigation of said impacts, the development of a Social and Environmental Management Plan, public information and consultations, determination of appropriate compensation for right-of-way expropriations, the preparation of a relocation plan, and, finally, submission of recommendations regarding training for the staff of government departments/agencies responsible for the environment. |
Environmental and social impact survey (Malian territory) of the Ivory Coast – Mali 225-kV (400 km) power interconnection
Client:
|
EDM SA |
Date: |
2007-08 |
Partenr: |
NONE |
Cost of services: |
55 million FCFA (84 000 €) |
Description : |
The project consisted in the definition of a legal and institutional framework, the determination of an environmental baseline, the development of a social and environmental impact assessment, the identification of potential mitigation of said impacts, the development of a Social and Environmental Management Plan, public information and consultations, determination of appropriate compensation for right-of-way expropriations, the preparation of a relocation plan, and, finally, submission of recommendations regarding training for the staff of government departments/agencies responsible for the environment. |
|
|
 |
|
 |