The project included:
The construction of gabion and mortared flagstone retaining walls over a distance of 7 km;
The construction of two concrete vehicular bridges and six footbridges;
The road and drainage works connecting to these crossings (4 km) ;
The paving with local flagstone of the pedestrian walkway along the collector and exterior lighting;
The construction of thirty neighbourhood squares and fenced-in green spaces;
The construction of small neighbourhood sewage systems to prevent black water evacuation toward the collector.
The project included four phases:
Phase 1: Collector retaining wall design;
Phase 2: Supervision of construction of the above design;
Phase 3: Design of the neighbourhood squares and green areas, bridges and footbridges and design of the neighbourhood sewage systems;
Phase 4: Supervision of the construction of the bridges and footbridges. |